The following is a summary of transactions between Select Energy, Inc.
and Northeast Utilities Service Company in accordance with the NU Operating
Companies' Service Agreement No. 85 under FERC Tariff Original Volume
No. 6 and Service Agreement No. 55 under FERC Tariff First Revised
Volume No. 7.
December 1, 1998 through
December 7, 1998*
* Transaction cancelled by Parties.
200MW
System Power - Pumped Storage
| Energy Reservation Charge |
3.15 |
$/kW-month |
| Energy Charges: |
|
|
|
Peak
|
150.00 |
$/MWh |
|
Off-Peak
|
150.00 |
$/MWh |
|
Shoulder
|
|
$/MWh |
0100 hours April 5,
1999 through 2400 hours April 30, 1999
two, 50MW blocks
| Northfield Mountain Unit Entitlement |
0.25* |
$/kW-week |
| Energy Charges: |
|
|
|
Peak
|
|
cents/kWh |
|
Off-Peak
|
|
cents/kWh |
|
Shoulder
|
|
cents/kWh |
* For the last partial week in April, 1999, the 26th through the 30th,
the charge rate was $0.18/kW-week,
prorated to account for five days instead of the full seven days in a
weekly cycle.

|